Recently, Weichai has completed the tests for the 2000kW Weichai 12M55 generator set, applied to Data Center, including: full load test, overload test and 100 times 0-100% start test
Previously, at the end of 2024, this unit was tested for continuous operation for 242 hours without any incidents. To ensure the authenticity of the data collection, the Weichai engineering team deployed an intelligent operating system, integrated with a Fluke power quality analyzer, a thermal camera, and two RC-integrated dummy loads. The entire testing process was recorded in real time by high-definition equipment and transmitted live for customers to follow.
The rapid development of global artificial intelligence has led to explosive growth in data computing power, data centers have extremely high requirements for backup power for generator sets. Weichai is proud to provide reliable power solutions for the construction of large data centers.